Digital Realty Data Center is a mapped data center in Maricopa County, AZ, operated by Digital Realty Trust, Inc.. DataCentersExposed has documented a 67,568 sq ft footprint at this site.
Reporting by Eric Keller · Updated Jun 14, 2026
Most sites are mapped — located but awaiting a second source. How we verify
Dot size = disclosed capacity (MW). Smallest = undisclosed, not small.
Overview
source: linkDigital Realty Data Center is a mapped colocation site in Tempe, Maricopa County, Arizona, run by Digital Realty Trust, Inc. Public records put its footprint at 67,568 square feet. No ultimate parent above Digital Realty Trust is identified in available records.
Operator chain
- Ultimate parentDigital Realty Trust, Inc.
- Files asDigital Realty Trust, Inc.
- This facilityDigital Realty Data Center
In the news
source: Google News- 4 Singapore data centre REITs with dividend yields of up to 8%. What income investors may want to watchBeansprout· Jun 9, 2026
- Digital Realty drops $9M per acre on Vernon data center siteThe Real Deal· Nov 7, 2025
- The Power to ChangeSite Selection Magazine· Nov 2, 2024
- Bankruptcy court approves Cyxtera sale to BrookfieldData Center Dynamics· Nov 17, 2023
- News | Brookfield Agrees To Acquire Cyxtera’s Data Centers for $775 MillionCoStar· Nov 1, 2023
- Cyxtera Data Center Leases – Who and What is at Risk?Dgtl Infra· Jul 6, 2023
Data-center discussions in Maricopa County
source: LocalView (CC0)Local-government meetings in this county that discussed data centers, each cued to the moment. From the public LocalView corpus of government meetings on YouTube — a county-level signal, not necessarily about this specific site.
Tax breaks & subsidies
source: Good Jobs First / GASB 77These tax breaks are recorded to Digital Realty Trust, Inc. (the operator/parent) and may cover this or other sites — no state names the recipient at the facility level.
- Texas Qualifying Data Center Exemption$0State of Texas · granted 2025 · term — yr · source
- Texas Qualifying Data Center Exemption$0State of Texas · granted 2022 · term — yr · source
- Texas Qualifying Data Center Exemption$0State of Texas · granted 2022 · term — yr · source
- Texas Qualifying Data Center Exemption$0State of Texas · granted 2014 · term — yr · source
Arizona reported $38.5M in Computer Data Center TPT/Use Tax Exemption (Deduction Code 565; A.R.S. § 41-1519) for FY2025 (Arizona Department of Revenue, Office of Economic Research and Analysis). Program-wide, not attributable to this site.
Water use
No measured record exists, so this is a low-confidence model from 5 MW (interconnection capacity): 2.5 L/kWh cooling (arid climate) + 0.45 gal/kWh embedded in US grid average. How we estimate. Have a utility document? Send it and we'll replace this with the real figure.
EPA permits & violations
source: EPA ECHONo reported violations as of last sync.
Air quality near this site
source: AirNowAir Quality Index from the nearest AirNow reporting area (Gila River Indian Community), as of 2026-06-10. Regional context — not this facility's own emissions.
Who lives nearby
source: Census ACS 2023Demographics of the census tract this facility sits in (American Community Survey 5-year estimates). Environmental-justice context for who bears the local impacts.
Nearest school
source: HIFLD / NCESThe nearest public school, Center For Educational Excellence in Tempe, is 0.9 mi from this site (319 students).
Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).
Hearings timeline
No public-hearing records linked to this site yet. We surface planning-commission and board-of-supervisors dates when a record names a facility. If you know of a hearing on this site, tell us.