Meta Prineville

Prineville, Crook County, OR

Meta Prineville is a mapped data center in Crook County, OR, operated by Facebook USA, Inc. and ultimately owned by Meta Platforms, Inc.. DataCentersExposed has documented 540 MW of reported power capacity at this site.

Reporting by · Updated Jun 14, 2026

Real parent
Meta Platforms, Inc.
Operator
Facebook USA, Inc.
Power
540 MW
Utility
Bonneville Power Administration
Grid
BPAT
Attribution & capacity confidence:mediumprovenance JSON
Status · click to filter

Most sites are mapped — located but awaiting a second source. How we verify

Dot size = disclosed capacity (MW). Smallest = undisclosed, not small.

Overview

Meta Prineville is a hyperscale data center in Prineville, Crook County, Oregon, operated by Facebook USA, Inc. and ultimately owned by Meta Platforms, Inc. Operational since 2011, the site draws on a reported power capacity of 540 MW, supplied by the Bonneville Power Administration within the BPAT balancing authority.

Operator chain

In the news

source: GDELT

Tax breaks & subsidies

source: Good Jobs First / GASB 77

These tax breaks are recorded to Meta Platforms, Inc. (the operator/parent) and may cover this or other sites — no state names the recipient at the facility level.

Dollar value not disclosed for this record.
  • Texas Qualifying Large Data Center Project Exemption$0
    State of Texas · granted 2022 · term yr · source
Statewide cost of this incentive

Oregon reported $26.9M in Enterprise Zone (Long-Term Rural EZ, ORS 285C.400) property-tax abatement — Crook County (Meta Prineville campus) for FY2025 (Crook County, Oregon (audited financial statements / GASB 77 note)). Program-wide, not attributable to this site.

source · All Oregon subsidies →

Water use

Modeled estimate~8M gpd
Direct (onsite cooling)
~3.3M gpd
Indirect (its electricity)
~4.7M gpd

No measured record exists, so this is a low-confidence model from 540 MW (disclosed IT power): 1.2 L/kWh cooling (cool climate) + 0.45 gal/kWh embedded in US grid average. How we estimate. Have a utility document? Send it and we'll replace this with the real figure.

EPA permits & violations

source: EPA ECHO

No reported violations as of last sync.

Air quality near this site

source: AirNow
8
PM2.5
Good

Air Quality Index from the nearest AirNow reporting area (Prineville), as of 2026-06-10. Regional context — not this facility's own emissions.

Who lives nearby

source: Census ACS 2023
Median household income
$84.7K
People of color
8%
Below poverty
4%
Tract population
3,469

Demographics of the census tract this facility sits in (American Community Survey 5-year estimates). Environmental-justice context for who bears the local impacts.

Nearest school

source: HIFLD / NCES

The nearest public school, Crook County Middle School in Prineville, is 1,015 ft from this site (617 students). 6 public schools sit within a mile of the site.

Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).

Hearings timeline

No public-hearing records linked to this site yet. We surface planning-commission and board-of-supervisors dates when a record names a facility. If you know of a hearing on this site, tell us.