Maricopa Data Center is a proposed data center in Maricopa County, AZ, operated by Fortescue.

Reporting by · Updated Jun 18, 2026

Campaign · Decision pending

Take action

Maricopa, Arizona

0
supporters

Maricopa Data Center in Buckeye, AZ is contested. Petition: https://www.change.org/p/stop-the-building-of-a-data-center-in-our-community Track what's being decided, when, and how to weigh in.

Hearing timeline

  1. DecisionCity Council Formal MeetingApproved

    Wed, Jan 21, 2026 · 2:30 PM MST

    City Council Formal Meeting: data-center item — Binding Waiver of Enforcement of Special Permit Provisions for Data Centers for Sheely Center.

    Approved — binding waiver of data-center special permit provisions adopted as amended/revised.

    Meeting detailsvia Legistar
  2. DecisionCity Council Formal MeetingDeferred

    Wed, Dec 17, 2025 · 2:30 PM MST

    City Council Formal Meeting: data-center item — Binding Waiver of Enforcement for Sheely Center data center special permit provisions.

    Continued — item postponed to a later date, no final decision

    Meeting detailsvia Legistar
  3. DecisionCity Council Formal MeetingDeferred

    Wed, Dec 3, 2025 · 2:30 PM MST

    City Council Formal Meeting: data-center item — Binding Waiver of Enforcement for Data Center special permit provisions (Sheely Center).

    Continued to December 17, 2025 meeting — no final decision made.

    Meeting detailsvia Legistar
  4. DecisionCity Council Formal MeetingDeferred

    Wed, Nov 19, 2025 · 2:30 PM MST

    City Council Formal Meeting: data-center item — Waiver of special permit provisions for data centers (Ordinance S-52435) continued.

    Continued to December 3, 2025 City Council Formal Meeting — no final decision.

    Meeting detailsvia Legistar
  5. City Council

    Tue, Jul 8, 2025 · 5:45 PM MST

    City Council: data-center item — Data center text amendments under discussion.

    AgendaMeeting detailsvia Legistar · medium confidence
  6. City Council

    Tue, Jul 1, 2025 · 5:45 PM MST

    City Council: data-center item — Data Center Text Amendment Resolution introduced.

    AgendaMeeting detailsvia Legistar · medium confidence
  7. Planning and Zoning Board - Public Hearing

    Wed, Jun 25, 2025 · 4:00 PM MST

    Planning and Zoning Board - Public Hearing: data-center item — Data center text amendment under consideration.

    AgendaMeeting detailsvia Legistar · medium confidence
  8. Planning and Zoning Board - Public Hearing

    Wed, Jun 11, 2025 · 4:00 PM MST

    Planning and Zoning Board - Public Hearing: data-center item — General text amendment regarding data centers

    AgendaMeeting detailsvia Legistar · medium confidence

Never miss a meeting: subscribe in your calendar · download .ics

Your action kit

Sourced arguments and ready-to-send letters — every figure links to a primary record. Edit to add your own story.

Process

Demand a full, public review — not a rubber stamp.

Ask for an independent noise study, a water-and-power impact assessment, enforceable conditions (setbacks, hours, cooling type), and that the record stays open for written comment. Procedural shortcuts have voided approvals elsewhere.

Public comment (editable)

Edit freely before sending — it's a starting point. Add your own story; personal comments carry the most weight.

Records / FOIA request

Edit freely before sending — it's a starting point. Add your own story; personal comments carry the most weight.

Join the campaign

Add your name and we'll email you before every hearing, with what to say and where to show up.

Helps show local strength to officials.

Double opt-in — confirm by email. We'll only email you about this campaign's hearings and milestones. Unsubscribe any time. We never share or sell your address. See our privacy policy.

Neighbors taking a stand

Be the first to say why this matters. Public notes appear here to show officials the strength of local feeling.
Real parent
Operator
Fortescue
Attribution & capacity confidence:mediumprimary source

Overview

source: link

On a site that Fortescue formerly planned to build a hydrogen production plant on, it is unclear whether the proposed data center plan would include a hydrogen plant. On February 10 2026, the Buckeye Area and Planning Commission voted to recommend the approval of a request to modify the zoning of a 158 acre land parcel, now awaiting Buckeye City Council approval. Imported from the FracTracker Alliance U.S. Data Centers Tracker after review. Details to be corroborated from primary sources.

Operator chain

  • Files as
    Fortescue
  • This facility
    Maricopa Data Center

Grid & water — why here

source: HIFLD · EPA
Nearest substation
3.3 mi
Unknown301046 · 238 kV
Transmission line
1.5 mi
238 kV line
Municipal water
No service area
self-supplied or unmapped

The closest existing grid infrastructure and the municipal water system this location sits in — the same constraints the buildout model screens on (it won't site a campus more than ~2 km from a substation or ~5 km from municipal water). Distances are straight-line to public HIFLD/EPA features, not a metered connection.

Data-center discussions in Maricopa County

source: LocalView (CC0)

Local-government meetings in this county that discussed data centers, each cued to the moment. From the public LocalView corpus of government meetings on YouTube — a county-level signal, not necessarily about this specific site.

Phoenix Committee
Jun 14, 2023 · 1 data-center mention
Chandler City Council
Oct 14, 2021 · 1 data-center mention
Chandler City Council
Sep 14, 2020 · 1 data-center mention

Tax breaks & subsidies

source: Good Jobs First / GASB 77

No per-deal tax break is linked to this site yet. No state discloses the recipient of a data-center abatement at the facility level, so per-site deals are rare in the public record. If you have a development agreement or board resolution for this site, send it to us.

Statewide cost of this incentive

Arizona reported $38.5M in Computer Data Center TPT/Use Tax Exemption (Deduction Code 565; A.R.S. § 41-1519) for FY2025 (Arizona Department of Revenue, Office of Economic Research and Analysis). Program-wide, not attributable to this site.

source · All Arizona subsidies →

Water use

No public record of this facility's water use. We check state withdrawal reporting for self-supplied sites; municipally supplied sites only become visible through a public-records request to the local water utility — a per-facility request tool is coming. If you have a utility document for this site, send it to us.

EPA permits & violations

source: EPA ECHO

No reported violations as of last sync.

Nearest school

source: HIFLD / NCES

The nearest public school, Palo Verde Elementary School in Palo Verde, is 10.9 mi from this site (446 students).

Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).

Hearings timeline