Element Critical CH1
711 North Edgewood Avenue · Wood Dale, DuPage County, IL
Source: OpenStreetMap
Element Critical CH1 is an operating data center in DuPage County, IL, operated by Element Critical. DataCentersExposed has documented a 92,076 sq ft footprint at this site.
Reporting by Eric Keller · Updated Jun 14, 2026
Most sites are mapped — located but awaiting a second source. How we verify
Dot size = disclosed capacity (MW). Smallest = undisclosed, not small.
Overview
source: linkElement Critical CH1 is an operating colocation data center in Wood Dale, DuPage County, Illinois, run by Element Critical. Public records put its footprint at 92,076 square feet. The site draws power from Commonwealth Edison Co inside the PJM grid.
Operator chain
- Ultimate parentElement Critical
- Files asElement Critical
- This facilityElement Critical CH1
In the news
source: GDELTNo recent coverage found for this facility.
Data-center discussions in DuPage County
source: LocalView (CC0)Local-government meetings in this county that discussed data centers, each cued to the moment. From the public LocalView corpus of government meetings on YouTube — a county-level signal, not necessarily about this specific site.
Tax breaks & subsidies
source: Good Jobs First / GASB 77No per-deal tax break is linked to this site yet. No state discloses the recipient of a data-center abatement at the facility level, so per-site deals are rare in the public record. If you have a development agreement or board resolution for this site, send it to us.
Illinois reported $983.2M in Data Center Investment Program — state & local sales/use tax exemption (20 ILCS 605/605-1025; administered by DCEO) (2019-2024 (27 certified data centers; cumulative estimated exemption value)) (Illinois Department of Commerce and Economic Opportunity (DCEO)). Program-wide, not attributable to this site.
Water use
No measured record exists, so this is a low-confidence model from 5 MW (interconnection capacity): 1.8 L/kWh cooling (temperate climate) + 0.5 gal/kWh embedded in PJM grid mix. How we estimate. Have a utility document? Send it and we'll replace this with the real figure.
EPA permits & violations
source: EPA ECHONo reported violations as of last sync.
What this site costs the grid
source: PJM RPM auction reportsPJM's capacity auction sets a $/MW-day price that utilities pass on to every household and business in the zone. This site sits in PJM's COMED pricing zone, where soaring data-center demand is a documented driver. See the full zone-by-zone breakdown →
An estimated ~15 to 40 MW of load at the zone's $333/MW-day, annualized — the capacity charge a load this size carries at the current auction price. Estimated from the building footprint at 200 to 400 W/ft² (the typical range for modern data centers). A rough order-of-magnitude figure, not a metered or permitted capacity.
Separately, a typical home in this zone pays an estimated $4 to $10/mo more on the capacity portion of its bill that PJM's market monitor attributes to data-center demand. See your address's full impact →
Air quality near this site
source: AirNowAir Quality Index from the nearest AirNow reporting area (Chicago), as of 2026-06-10. Regional context — not this facility's own emissions.
Who lives nearby
source: Census ACS 2023Demographics of the census tract this facility sits in (American Community Survey 5-year estimates). Environmental-justice context for who bears the local impacts.
Nearest school
source: HIFLD / NCESThe nearest public school, Wood Dale Jr High School in Wood Dale, is 0.7 mi from this site (294 students). 3 public schools sit within a mile of the site.
Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).
Hearings timeline
No public-hearing records linked to this site yet. We surface planning-commission and board-of-supervisors dates when a record names a facility. If you know of a hearing on this site, tell us.