CyrusOne/Eolian Data Center
Fort Worth, Tarrant County, TX
Source: Primary source
CyrusOne/Eolian Data Center is a under construction data center in Tarrant County, TX, operated by CyrusOne/Eolian. DataCentersExposed has documented 70 MW of reported power capacity and a 1,900,000 sq ft footprint at this site.
Reporting by Eric Keller · Updated Jun 18, 2026
Take action
Tarrant, Texas
CyrusOne/Eolian Data Center in Fort Worth, TX is contested. Petition: https://www.change.org/p/stop-the-data-center-next-to-our-historic-gardens-for-all-supporters-sign-petition-below Track what's being decided, when, and how to weigh in.
Your action kit
Sourced arguments and ready-to-send letters — every figure links to a primary record. Edit to add your own story.
70 MW of new demand — roughly a city of 56,000 homes.
Large new loads can raise transmission and capacity costs that land on every ratepayer. Residential power in TX is 16.4¢/kWh, up 7.3% year-over-year. (MW→homes is a rough ~800/MW planning figure.)
SourceDemand a full, public review — not a rubber stamp.
Ask for an independent noise study, a water-and-power impact assessment, enforceable conditions (setbacks, hours, cooling type), and that the record stays open for written comment. Procedural shortcuts have voided approvals elsewhere.
Edit freely before sending — it's a starting point. Add your own story; personal comments carry the most weight.
Edit freely before sending — it's a starting point. Add your own story; personal comments carry the most weight.
Join the campaign
Add your name and we'll email you before every hearing, with what to say and where to show up.
Neighbors taking a stand
Overview
source: linkBESS battery storage co-location Imported from the FracTracker Alliance U.S. Data Centers Tracker after review. Details to be corroborated from primary sources.
Operator chain
- Files asCyrusOne/Eolian
- This facilityCyrusOne/Eolian Data Center
Grid & water — why here
source: HIFLD · EPAThe closest existing grid infrastructure and the municipal water system this location sits in — the same constraints the buildout model screens on (it won't site a campus more than ~2 km from a substation or ~5 km from municipal water). Distances are straight-line to public HIFLD/EPA features, not a metered connection.
In the news
source: Google News- Eolian monetizes its BESS grid connection for new Texas data centerESS News· Jan 23, 2026
- A Texas data center will open sooner thanks to an offline grid batteryCanary Media· Jan 22, 2026
- Geico Expands DFW Footprint With Third Location and Dallas Cowboys PartnershipD Magazine· Jan 16, 2026
- CyrusOne partners with energy firm Eolian for Dallas data centerData Center Dynamics· Jan 14, 2026
- Eolian and CyrusOne team up to deploy Texas data centre at site of 100MW BESSEnergy-Storage.News· Jan 14, 2026
- CyrusOne and Eolian Partner to Enable Rapid Deployment of 200 Megawatt Data Center Campus in Fort Worth, TexasPR Newswire· Jan 13, 2026
Tax breaks & subsidies
source: Good Jobs First / GASB 77No per-deal tax break is linked to this site yet. No state discloses the recipient of a data-center abatement at the facility level, so per-site deals are rare in the public record. If you have a development agreement or board resolution for this site, send it to us.
Texas reported $16.1M in Property used in certain large data center projects; temporary exemption (Texas Tax Code § 151.3595) for FY2025 (Texas Comptroller of Public Accounts). Program-wide, not attributable to this site.
Water use
No public record of this facility's water use. We check state withdrawal reporting for self-supplied sites; municipally supplied sites only become visible through a public-records request to the local water utility — a per-facility request tool is coming. If you have a utility document for this site, send it to us.
EPA permits & violations
source: EPA ECHONo reported violations as of last sync.
Nearest school
source: HIFLD / NCESThe nearest public school, Lake Pointe El in Fort Worth, is 1.3 mi from this site (669 students).
Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).
Hearings timeline
No public-hearing records linked to this site yet. We surface planning-commission and board-of-supervisors dates when a record names a facility. If you know of a hearing on this site, tell us.