Compute North
Buffalo County, NE
Source: OpenStreetMap
Compute North is a mapped data center in Buffalo County, NE. DataCentersExposed has documented a 353,355 sq ft footprint at this site.
Reporting by Eric Keller · Updated Jun 14, 2026
Most sites are mapped — located but awaiting a second source. How we verify
Dot size = disclosed capacity (MW). Smallest = undisclosed, not small.
Overview
source: linkdata center
The grid behind this site, right now
source: SPP · gridstatus- Wind40.1%
- Coal24.7%
- Natural Gas24.7%
- Nuclear6.2%
- Hydro4.2%
Real-time generation mix for the SPP grid this site draws from, as of Jun 16, 2026, 9:25 AM. ISO-wide, not this facility's own metering. Source: gridstatus.
In the news
source: Google News- Amazon cloud outage at North Virginia data center largely resolvedReuters· May 8, 2026
- Point Pleasant data center: 3 buildings, nearly 1,000 natural gas, diesel enginesCharleston Gazette-Mail· May 2, 2026
- Massive 1 GW Data Centre Planned For North LincolnshireSilicon UK· Mar 16, 2026
- North America Data Center Report Year-end 2025JLL· Feb 17, 2026
- North America Data Center Liquid Cooling Market ReportMarket Data Forecast· Feb 11, 2026
- North America Data Center GPU Market Report 2025 - 2030 [230 Pages & 150 Tables]MarketsandMarkets· Jan 22, 2026
Tax breaks & subsidies
source: Good Jobs First / GASB 77No per-deal tax break is linked to this site yet. No state discloses the recipient of a data-center abatement at the facility level, so per-site deals are rare in the public record. If you have a development agreement or board resolution for this site, send it to us.
Nebraska reported $5.7M in Data Centers sales/use tax exemption (Neb. Rev. Stat. § 77-2704.62) for FY2025 (Nebraska Department of Revenue). Program-wide, not attributable to this site.
Water use
No public record of this facility's water use. We check state withdrawal reporting for self-supplied sites; municipally supplied sites only become visible through a public-records request to the local water utility — a per-facility request tool is coming. If you have a utility document for this site, send it to us.
EPA permits & violations
source: EPA ECHONo reported violations as of last sync.
Air quality near this site
source: AirNowAir Quality Index from the nearest AirNow reporting area (Grand Island), as of 2026-06-10. Regional context — not this facility's own emissions.
Who lives nearby
source: Census ACS 2023Demographics of the census tract this facility sits in (American Community Survey 5-year estimates). Environmental-justice context for who bears the local impacts.
Nearest school
source: HIFLD / NCESThe nearest public school, Sunrise Middle School in Kearney, is 1.4 mi from this site (577 students).
Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).
Hearings timeline
No public-hearing records linked to this site yet. We surface planning-commission and board-of-supervisors dates when a record names a facility. If you know of a hearing on this site, tell us.