Source: Primary source

Stack Northern Virginia NVA05 is a permitted data center in Prince William County, VA. DataCentersExposed has documented a 326,500 sq ft footprint at this site.

Reporting by · Updated Jun 16, 2026

Campaign · Approved

Take action

Prince William, Virginia

0
supporters

It was approved. The fight shifts to enforceable conditions, monitoring, and the next one.

Your action kit

Sourced arguments and ready-to-send letters — every figure links to a primary record. Edit to add your own story.

Process

Demand a full, public review — not a rubber stamp.

Ask for an independent noise study, a water-and-power impact assessment, enforceable conditions (setbacks, hours, cooling type), and that the record stays open for written comment. Procedural shortcuts have voided approvals elsewhere.

Public comment (editable)

Edit freely before sending — it's a starting point. Add your own story; personal comments carry the most weight.

Records / FOIA request

Edit freely before sending — it's a starting point. Add your own story; personal comments carry the most weight.

Join the campaign

Add your name and we'll email you before every hearing, with what to say and where to show up.

Helps show local strength to officials.

Double opt-in — confirm by email. We'll only email you about this campaign's hearings and milestones. Unsubscribe any time. We never share or sell your address. See our privacy policy.

Neighbors taking a stand

Be the first to say why this matters. Public notes appear here to show officials the strength of local feeling.
Real parent
Operator
Est. capacity
~65-140 MW
Footprint
326,500 sq ft
Utility
Northern Virginia Elec Coop
Grid
PJM
Attribution & capacity confidence:highprimary source
Status · click to filter

Most sites are mapped — located but awaiting a second source. How we verify

Dot size = disclosed capacity (MW). Smallest = undisclosed, not small.

Overview

source: link

Data-center campus in Prince William County, Virginia (status: permitted). Case(s): REZ2023-00026. Source: PWC County Mapper Data Center Campuses layer.

Tax breaks & subsidies

source: Good Jobs First / GASB 77

No per-deal tax break is linked to this site yet. No state discloses the recipient of a data-center abatement at the facility level, so per-site deals are rare in the public record. If you have a development agreement or board resolution for this site, send it to us.

Statewide cost of this incentive

Virginia reported $1B in Data Center Retail Sales and Use Tax Exemption (Va. Code § 58.1-609.3(18)) for FY2024 (Virginia Joint Legislative Audit and Review Commission (JLARC) / Weldon Cooper Center). Program-wide, not attributable to this site.

source · All Virginia subsidies →

Water use

No public record of this facility's water use. We check state withdrawal reporting for self-supplied sites; municipally supplied sites only become visible through a public-records request to the local water utility — a per-facility request tool is coming. If you have a utility document for this site, send it to us.

EPA permits & violations

source: EPA ECHO

No reported violations as of last sync.

What this site costs the grid

source: PJM RPM auction reports
Dominion (Virginia / NC) · 2027/28 auction
$333 /MW-day
Peaked at $444/MW-day in 2025/26 1.65× the rest of PJM

PJM's capacity auction sets a $/MW-day price that utilities pass on to every household and business in the zone. This site sits in PJM's DOM pricing zone, where soaring data-center demand is a documented driver. See the full zone-by-zone breakdown →

This site's capacity-market cost (estimated)
$7.9M to $17M/yr

An estimated ~65 to 140 MW of load at the zone's $333/MW-day, annualized — the capacity charge a load this size carries at the current auction price. Estimated from the building footprint at 200 to 400 W/ft² (the typical range for modern data centers). A rough order-of-magnitude figure, not a metered or permitted capacity.

Separately, a typical home in this zone pays an estimated $4 to $10/mo more on the capacity portion of its bill that PJM's market monitor attributes to data-center demand. See your address's full impact →

Nearest school

source: HIFLD / NCES

The nearest public school, Unity Reed High in Manassas, is 0.5 mi from this site (2,316 students). 2 public schools sit within a mile of the site.

Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).

Hearings timeline

No public-hearing records linked to this site yet. We surface planning-commission and board-of-supervisors dates when a record names a facility. If you know of a hearing on this site, tell us.