Mapped (unverified)colocation
DC2-Telemark
Rjukan, Telemark, Norway
Source: Primary source
DC2-Telemark is a mapped data center in Telemark, Norway, operated by Green Mountain. It runs on Norway's grid, which was 1% fossil-fuelled at 28 gCO₂e/kWh in 2025 (Ember).
Reporting by Eric Keller · Updated Jun 17, 2026
Real parent
Green Mountain
Operator
Green Mountain
Grid carbon
28 gCO₂/kWh
Clean electricity
99%
DC power price
6.47¢/kWh
Region
Telemark
Overview
source: linkGreen Mountain AS — colocation facility (1 networks present). Source: PeeringDB.
Operator chain
- Ultimate parentGreen Mountain
- Files asGreen Mountain
- This facilityDC2-Telemark
The grid behind this site
source: Ember · EurostatGrid carbon intensity
28 gCO₂/kWh
Clean electricity
99%
Fossil electricity
1%
Data-center power price
6.47¢/kWh
A large data center in Norway pays 6.47¢/kWh for electricity — a household pays 19.02¢, 66% more than the data center (Eurostat).
National grid context, not this facility's own metering. Full country picture: Norway data centers.
In the news
source: Google News (local + English)- – Datasenter har vært positivt for kommunendriva.no· May 11, 2026
- Green Mountain vil samarbeide med lokalt idrettslag: – Er i dialogStavanger Aftenblad· Mar 19, 2026
- Datasenter vurderes i Rollag: Kan gi mange nye arbeidsplasser og milliardinvesteringLaagendalsposten· Mar 12, 2026
- Green Mountain åpner for søknader til årets Community Support FundMynewsdesk· Feb 12, 2026
- Overskuddsvarme fra datasenter: En løsning for bærekraftig oppdrettNRK· Feb 7, 2026
- Datasenter og industri: Her går mesteparten av overskuddsvarmen taptDigi.no· Feb 6, 2026
See something wrong or missing on this page? Suggest a correction.